Pending COs
1
awaiting approval
CO Value (Approved)
$57,250
+10 schedule days
Submittals In Review
3
under review
Submittals Approved
8
of 12 total
CO-001Approved+5 days
Soil Remediation — Unexpected Fill Material
Unsuitable fill material discovered at 4ft depth — required removal and engineered fill replacement.
Submitted Sep 18, 2025Approved Sep 22, 2025By Jake Thornton
$22,400
CO-002Approved+3 days
Foundation Depth Increase — Frost Line
Engineer directed 12" additional depth on north wall footings per frost depth requirements.
Submitted Oct 5, 2025Approved Oct 8, 2025By Jake Thornton
$8,750
CO-003Approved
Electrical Service Upgrade — 400A to 600A
Tenant load calculations required service upgrade to accommodate Wellness Collective equipment.
Submitted Nov 10, 2025Approved Nov 14, 2025By Jake Thornton
$11,200
CO-004Approved+2 days
Added Storefront Entry — Suite 102
Owner requested separate exterior entry for co-work space.
Submitted Jan 8, 2026Approved Jan 12, 2026By Jake Thornton
$6,800
CO-005Approved
Plumbing Reroute — City Comment Response
City plan check required reroute of main sanitary line to avoid conflict with structural beam.
Submitted Feb 20, 2026Approved Feb 24, 2026By Jake Thornton
$4,200
CO-006Approved
Acoustic Ceiling Upgrade — Law Office
Sargent Law Firm requested upgraded acoustic ceiling tile for client confidentiality.
Submitted Mar 15, 2026Approved Mar 18, 2026By Jake Thornton
$3,900
CO-007Pending+4 days
Structural Steel Upgrade — Roof Deck
Structural engineer directed heavier gauge steel deck at roof to meet revised snow load calculations per updated IBC.
Submitted Apr 22, 2026By Jake Thornton
$14,200