Current Phase

Framing & Structural

3 of 8 milestones complete

38%

Overall Complete

Start: Sep 1, 2025Est. Completion: Aug 15, 2026
Contract Value
$2,850,000
Original contract
Approved COs
$57,250
6 change orders
Paid to Date
$769,500
3 pay apps
Pending Approvals
1
Awaiting action

Construction Milestones

Site Preparation & Demo
100%Complete

Sep 1, 2025Sep 30, 2025

Foundation & Concrete
100%Complete

Oct 1, 2025Nov 15, 2025

Structural Steel & Framing
100%Complete

Nov 16, 2025Jan 31, 2026

Framing & Rough-In
65%In Progress

Feb 1, 2026May 15, 2026

MEP Rough-In
30%In Progress

Mar 15, 2026Jun 1, 2026

Exterior Envelope
5%Upcoming

May 1, 2026Jul 1, 2026

Interior Finishes
0%Upcoming

Jun 1, 2026Aug 1, 2026

Punch List & Closeout
0%Upcoming

Aug 1, 2026Aug 15, 2026

Project Details

Owner
Ryan Williams / Wildly Built
General Contractor
Jake Thornton / Lodestar Construction
Designer
Erika Williams / Wildly Built Design
Building Size
5,400 sq ft · 2 stories
Zoning
C-17 Mixed Use Commercial

Tenant Spaces

Sargent Law Firm
Suite 101 · 1,400 sf
Meeting Room / Co-Work
Suite 102 · 800 sf
Ryan's Storage
Suite 201 · 1,600 sf
Wellness Collective
Suite 202 · 1,200 sf

Budget Snapshot

Original Contract$2,850,000
Approved Change Orders+$57,250
Revised Contract$2,907,250
Spent to Date$1,258,250
Spent43%

Recent Change Orders

CO-007Pending

Structural Steel Upgrade — Roof Deck

$14,200

+4 days

CO-006Approved

Acoustic Ceiling Upgrade — Law Office

$3,900

CO-005Approved

Plumbing Reroute — City Comment Response

$4,200

CO-004Approved

Added Storefront Entry — Suite 102

$6,800

+2 days