Permitting
City of Coeur d'Alene Building Department
Permits Issued
3
of 5 total
Under Review
2
awaiting city response
Open Comments
1
require response
Inspections
5
passed · 3 upcoming
Building Permit — Commercial New Construction
BP-2025-0847
Plan Check Fee
$8,450
- Submitted
- Jul 15, 2025
- Issued
- Aug 28, 2025
- Expires
- Aug 28, 2027
- Review Round
- Round 2
Issued after Round 2 corrections. All comments resolved.
Plan Check Comments (3)
Provide calculations for roof snow load per IBC Table 1608.2 for CDA zone.
Response:
Calculations provided by SE — see attached.
Accessible parking count insufficient per CBC 11B-208. Provide 2 van-accessible spaces.
Response:
Site plan revised — 2 van-accessible spaces added on A1.1 Rev 1.
Title 24 energy compliance forms not included in submittal.
Response:
Title 24 forms included in Round 2 submittal.
Mechanical Permit — HVAC
MP-2025-0312
Plan Check Fee
$1,850
- Submitted
- Nov 1, 2025
- Issued
- Nov 20, 2025
- Expires
- Nov 20, 2027
- Review Round
- Round 1
Issued on first submission.
Electrical Permit
EP-2025-0198
Plan Check Fee
$2,200
- Submitted
- Nov 1, 2025
- Issued
- Nov 18, 2025
- Expires
- Nov 18, 2027
- Review Round
- Round 1
Issued on first submission.
Plumbing Permit
PP-2026-0044
Plan Check Fee
$1,650
- Submitted
- Jan 10, 2026
- Issued
- —
- Expires
- —
- Review Round
- Round 2
Round 2 submitted 2/24/26 after plumbing reroute. Awaiting response.
Plan Check Comments (4)
Sanitary main conflicts with W8x31 beam at grid B-4. Reroute required.
Response:
Rerouted per CO-005. Revised plumbing plan submitted.
Water heater location does not have required seismic strapping detail.
Response:
Detail added to P-3 Rev 1.
Revised sanitary plan does not show cleanout at base of stack per UPC 707.4.
Response:
Cleanout added to P-2 Rev 2. Resubmitted 4/15/26.
Owner acknowledgment required for rerouted sanitary line affecting tenant Suite 101 slab.
Fire Sprinkler Permit
FSP-2026-0021
Plan Check Fee
$980
- Submitted
- Mar 1, 2026
- Issued
- —
- Expires
- —
- Review Round
- Round 1
Under initial review. Expected 3-4 weeks.