Permits Issued

3

of 5 total

Under Review

2

awaiting city response

Open Comments

1

require response

Inspections

5

passed · 3 upcoming

Issued

Building Permit — Commercial New Construction

BP-2025-0847

Plan Check Fee

$8,450

Submitted
Jul 15, 2025
Issued
Aug 28, 2025
Expires
Aug 28, 2027
Review Round
Round 2

Issued after Round 2 corrections. All comments resolved.

Plan Check Comments (3)

PC-2025-001StructuralResolved
Assigned: Erika Williams

Provide calculations for roof snow load per IBC Table 1608.2 for CDA zone.

Response:

Calculations provided by SE — see attached.

PC-2025-002AccessibilityResolved
Assigned: Erika Williams

Accessible parking count insufficient per CBC 11B-208. Provide 2 van-accessible spaces.

Response:

Site plan revised — 2 van-accessible spaces added on A1.1 Rev 1.

PC-2025-003EnergyResolved
Assigned: Erika Williams

Title 24 energy compliance forms not included in submittal.

Response:

Title 24 forms included in Round 2 submittal.

Issued

Mechanical Permit — HVAC

MP-2025-0312

Plan Check Fee

$1,850

Submitted
Nov 1, 2025
Issued
Nov 20, 2025
Expires
Nov 20, 2027
Review Round
Round 1

Issued on first submission.

Issued

Electrical Permit

EP-2025-0198

Plan Check Fee

$2,200

Submitted
Nov 1, 2025
Issued
Nov 18, 2025
Expires
Nov 18, 2027
Review Round
Round 1

Issued on first submission.

Under Review1 open comment

Plumbing Permit

PP-2026-0044

Plan Check Fee

$1,650

Submitted
Jan 10, 2026
Issued
Expires
Review Round
Round 2

Round 2 submitted 2/24/26 after plumbing reroute. Awaiting response.

Plan Check Comments (4)

PC-2026-011PlumbingResolved
Assigned: Jake Thornton

Sanitary main conflicts with W8x31 beam at grid B-4. Reroute required.

Response:

Rerouted per CO-005. Revised plumbing plan submitted.

PC-2026-012PlumbingResolved
Assigned: Erika Williams

Water heater location does not have required seismic strapping detail.

Response:

Detail added to P-3 Rev 1.

PC-2026-013PlumbingResponded
Assigned: Erika Williams

Revised sanitary plan does not show cleanout at base of stack per UPC 707.4.

Response:

Cleanout added to P-2 Rev 2. Resubmitted 4/15/26.

PC-2026-014PlumbingOpen
Assigned: Ryan Williams

Owner acknowledgment required for rerouted sanitary line affecting tenant Suite 101 slab.

Under Review

Fire Sprinkler Permit

FSP-2026-0021

Plan Check Fee

$980

Submitted
Mar 1, 2026
Issued
Expires
Review Round
Round 1

Under initial review. Expected 3-4 weeks.