Lobby Tile Selection

Two options presented: 24x24 Porcelain (Option A) vs 12x24 Marble-look (Option B). Lead time 6 weeks after order.

Attendees: Ryan Williams, Erika Williams

Decisions Made

DecidedOAC MeetingAug 15, 2025

Exterior Cladding Material

Decision

Hardie board lap siding — Arctic White with dark bronze storefront

Three options presented — fiber cement selected for durability and cost.

Decided by: Ryan WilliamsAttendees: Ryan Williams, Erika Williams, Jake Thornton
DecidedEmailNov 12, 2025

Electrical Service Size

Decision

Upgrade to 600A service to accommodate Wellness Collective load requirements

Tenant load calculations showed 400A insufficient. CO-003 issued.

Decided by: Ryan WilliamsAttendees: Ryan Williams, Erika Williams
DecidedOAC MeetingJan 10, 2026

Storefront Entry — Suite 102

Decision

Add separate exterior entry door for co-work space — CO-004 approved

Owner requested after co-work tenant requested dedicated entry.

Decided by: Ryan WilliamsAttendees: Ryan Williams, Erika Williams, Jake Thornton
DecidedOAC MeetingFeb 22, 2026

Roof System Selection

Decision

TPO membrane with R-30 insulation — Cascade Roofing awarded

TPO selected over EPDM for reflectivity and warranty terms.

Decided by: Ryan WilliamsAttendees: Ryan Williams, Erika Williams, Jake Thornton