Project Schedule
901 N 3rd Street · Est. Completion: Aug 15, 2026
Complete
3
phases done
In Progress
2
active phases
Upcoming
3
phases ahead
Overall
38%
complete
Phase Details
●
Site Preparation & Demo
Pre-Construction
Start: Sep 1, 2025100% completeEnd: Sep 30, 2025
●
Foundation & Concrete
Foundation
Start: Oct 1, 2025100% completeEnd: Nov 15, 2025
●
Structural Steel & Framing
Structure
Start: Nov 16, 2025100% completeEnd: Jan 31, 2026
◑
Framing & Rough-In
Framing
Start: Feb 1, 202665% completeEnd: May 15, 2026
◑
MEP Rough-In
MEP
Start: Mar 15, 202630% completeEnd: Jun 1, 2026
○
Exterior Envelope
Exterior
Start: May 1, 20265% completeEnd: Jul 1, 2026
○
Interior Finishes
Interior
Start: Jun 1, 20260% completeEnd: Aug 1, 2026
○
Punch List & Closeout
Closeout
Start: Aug 1, 20260% completeEnd: Aug 15, 2026